Release Planner

Forecast a release from the backlog or a story-map slice and the team's real velocity: the date to commit to, and the chance of hitting the one stakeholders ask about.

How this works

The Release Planner forecasts when a release will be done by replaying your past sprints' velocity, or items finished a week, 10,000 times (a Monte Carlo simulation). You get a range, the date to commit to, and the chance of hitting a target date.

When to use it

  • When stakeholders ask “when will it be done?” about a release or a story-map slice.
  • Before committing to a date, to see how likely it is.
  • When scope changes, to show what that does to the date.

How to run it

  1. Under Forecast by, keep Story points, or pick Item count to forecast from items finished a week, with no points.
  2. Under Scope, pick Backlog (open stories' points), Story-map slice (Plan this release in the Story Mapper opens one here) or Type it. Expected scope change adds work not found yet.
  3. Under Velocity, use From completed sprints, or Type them: points per sprint, oldest first.
  4. Under Dates, check the Start and Sprint length, and add a Target date if there is one.
  5. Read the Forecast: the verdict, Coin flip (P50), Commit (P85), the chart and the dates at 50% to 95% confidence; with a target date, the Probability of finishing by then and the Scope we can deliver by then.
  6. In Item count, take Items left from Open backlog stories or Type a number, and the weekly counts under Throughput from the Sprint board, Flow board or Type them, over your Weeks of history. A week with no finish counts as 0. The Forecast adds Safe (P95) and, with a target date, By the target.
  7. Under Features in order, add each feature's Items or pick an epic, and order them. Each shows its coin-flip and commit dates, counting the ones above, and the target date draws the cut line. An epic with nothing left, or off the roadmap, counts 0.

Confidence

50%
a coin flip — half the simulated runs finished later
75%
likely, but a real chance of slipping
85%
a common choice for commitments
95%
very safe — use it when the date can't move

Tips

  • Commit to the P85 date, not the P50 one (a coin flip), and re-run it every sprint.
  • Story points need at least 4 sprints of velocity, completed or typed; Item count, 4 complete weeks with at least one finish. Unpointed stories or cards are left out of a points scope, so estimate them first.
  • If Change in pace (CUSUM) under Advanced analysis says the velocity shifted, forecast from the sprints since the change.

Scope

pts
%

Scope usually grows as the work is understood (10–25% is common). Negative for planned cuts.

Scope to forecast: not set yet.

Velocity

No completed sprints with points yet. Close them in Velocity, or type the numbers instead.

Dates

Today.

days

14 days, from the team's cadence (Team charter).

The date stakeholders ask about: see the chance of making it.

Amr, waiting
Nothing to forecast yet. Choose the scope and the velocity above, or load an example to see a forecast.