PI Planning Board

SAFe Program Increment board — teams × iterations with features, dependencies, and risks.

How this works

In SAFe, PI Planning is the event where all teams on an Agile Release Train plan the next Program Increment together. This board lays out teams against iterations so you can place features against each team's velocity, track dependencies on the Dependency Map and agree PI objectives.

When to use it

  • At the start of each Program Increment, usually every 8–12 weeks.
  • When several teams deliver one product and need to see each other's plans.
  • To check a draft plan against each team's capacity before committing.

Timebox: Usually two days, once per Program Increment

How to run it

  1. Under Add a team, add each team with its name and Velocity (points per iteration).
  2. Under Board, set Iterations in the PI. Five is SAFe's usual four development iterations plus one for innovation and planning.
  3. Click Add item in a team's iteration and choose its Kind: Feature, Dependency or Risk. Only features count toward the team's load.
  4. For a dependency, pick the team it Waits on and, if it has a deadline, the date it's Due: it goes on the Dependency Map, and its status shows on the card. Use Move to put any item in another cell.
  5. Watch each cell's planned / velocity points. A cell over capacity turns red: cut scope or move work to a later iteration. Load vs capacity charts every team.
  6. Under PI objectives, add each team's objectives as Committed or Uncommitted, and score Business value once the business owners have.

Business value

1–3
nice to have
4–6
clear value to the business
7–8
high value
9–10
critical to the business

Tips

  • Keep the last iteration free of features. In SAFe it's for innovation, planning and buffer.
  • Chase each open dependency's owner and due date on the Dependency Map.
  • Sort each risk as Resolved, Owned, Accepted or Mitigated (ROAM), and log the open ones in the Risk Register.

Teams
0
Feature points
0
no velocity set
Over capacity
0
team iterations
Open dependencies
0

Add a team

Points per iteration. Optional.

Optional

Amr, waiting
No teams on the board yet. Add the teams in the release train above, or load an example to see a planned PI.