Stacey Matrix

Plot work on Certainty (how) vs Agreement (what), 0–1. The plot region recommends a leadership approach.

How this works

The Stacey Matrix places work on two axes: how much people agree on what is needed, and how certain you are about how to do it. Where it lands suggests whether to plan, analyze, iterate or stabilize first.

When to use it

  • Deciding whether work suits a fixed plan or short iterations.
  • Explaining to stakeholders why some work can't be planned in detail up front.

How to run it

  1. Type the Item / problem.
  2. Score Agreement from 0 to 1: how much do stakeholders agree on what is needed? 1 is full agreement.
  3. Score Certainty from 0 to 1: how sure are you about how to build it? 1 means it's been done many times.
  4. Click Plot. The item appears on the Matrix and in its region list.
  5. Choose an approach for each region, and re-plot items as agreement and certainty change.

Regions

Simple
both 0.66 or more: plan and follow best practice
Complicated
one axis 0.66 or more, the other below 0.33: analyze or negotiate
Complex
everything in between: work in short, iterative cycles
Chaotic
both 0.33 or less: act to stabilize, then reassess

Tips

  • Score with the people involved. One person's view hides disagreement.
  • Most software work lands in Complex, which is why short iterations and feedback pay off.
  • For another angle on the same question, try the Cynefin Decision Picker.