Cost-of-Delay Tracker
CD3 = cost of delay per week ÷ duration in weeks, ordered by urgency profile: expedite now, fixed dates by latest start, then standard and intangible work by CD3.
How this works
Cost of Delay orders work by CD3: what a week of waiting costs, divided by the weeks the work takes, inside urgency lanes. Putting a number on waiting makes it visible.
Cost of Delay orders work by CD3: what a week of waiting costs, divided by the weeks the work takes, inside urgency lanes. Putting a number on waiting makes it visible.
When to use it
- Making the case for doing one initiative before another.
- When work waits in queues and nobody sees what the wait costs.
How to run it
- Type the Initiative title.
- Enter Cost of delay ($ per week): the revenue, savings or avoided risk lost each week it isn't live. Enter Duration (weeks), half a week at least. The CD3 they make shows as you type.
- Pick an Urgency profile: Expedite, Fixed date, Standard or Intangible (the line under it says what each means). For Fixed date, enter the Date it must land by. Then click Add.
- The list runs in lanes: Expedite first, then Fixed date by latest start (Start by … to land by …, marked late once that start has passed), then Standard and Intangible by CD3.
- Older items without a duration wait under Not scored: add a duration. Use Edit to add one.
Tips
- A rough range beats no number. Write down your assumptions so others can challenge them.
- Waiting costs $N per week is what one more week of the whole queue costs.
- Cross-check with the WSJF Calculator, which sizes the same trade-off relatively.
Add initiative

No initiatives yet. Add one above, or load an example queue with every urgency profile.